AP U DISE 2015-2016 Revised Schedule-AP UDISE Guidelines

AP U DISE 2015-2016 Schedule,Revised Schedule,AP Revised U-DISE Schedule SSA Guidelines Instructions

U-Dise 2015-16- Revised Tentative Time Frame For Activities

calender of activities,guidelines on udise 2015-16,certain instructions on udise 2015-16,ap ssa u-dise schedule and guidelines,dcf,AP SSA U-DISE Schedule and Guidelines
U-DISE 2015-2016

Sl. No. Item of work Proposed schedule
1
Finalization of School Directory for the Year 2015-16 at District Level.
:
01-09-15 to 10-09-15
2
Finalization of guidelines for Data Capture Format (DCF) and State Variables and Generation of data for the year 2015-16 at SPO
:
08-09-15 to 17-09-15
3
Printing of UDISE training manuals at SPO
:
By 21-09-15
4
One day Workshop for ASO, APOs, MIS Cor., ASO O/o. DEO on generation of data for the year 2015-16 & printing of UDISE DCF with UDISE S/W and Corrections of GPs, Habitation & Assembly Names in UDISE at State Level.
:
22-09-15
5
Printing of DCF through UDISE S/W at district Project Offices
:
23-09-15 to 28-09-15
6
Observing UDISE DAY
:
30-09-15
7
One day district level training to mandal teams @ 3 from each mandal (1 MEO, two MRG teachers), PMRC incharges, Dy.EOs, RIOs, DVEOs - not more than 50 participants in each spell and Distribution of DCFs

Note: Involve RMSA Staff.
:
Complete by

01-10-15
8
· One day mandal level training to CRPs/HMs (District MIS staff should attend to Mandal trainings as resource persons to the complicated mandals) and distribution of DCF.

· One day District Level training to Principals of Junior Collages by RIOs, DVEOs & Dy.E.Os and distribution of DCF.
:
Complete by

06-10-15
9
Filling up of Data Capture Formats by school HMs and Field Data Collection(Reference date 30th Sep 2014)
:
06-10-15 to 09-10-15
10
Scrutiny and Cross Checking of 100% Data Capture Formats at School Complex(CRP) Level
:
10-10-15 to 13-10-15
11
Two day state level training to ASO/APOs on UDISE software for data entry& Plan Tool Software by RMSA @ 3 from each district (ASO & APOs working in O/o DPO &ASO working in O/o DEO)
:
12-10-15 to 13-10-15
12
Scrutiny and Cross Checking of 25% Data Capture Formats at MRC Level
:
14-10-15 to 17-10-15
13
Submission of Data capture formats to District Project Office by MEOs as per Schedule
:
By 19-10-15
14
Arrangement of at least 15 systems for data entry at district level
:
By 19-10-15
15
One day training to Mandal MIS Coordinator / data entry operators for data entry at District Headquarters on UDISE software and entry procedures
:
By 26-10-15
16
Scrutiny and Cross checking of 5% DCF at District level
:
By 26-10-15
17
Data entry at the district level/Mandal level under the supervision of concerned MEOs / MRG Teachers / Mandal MIS Coordinators

Error Checking using Consistency Module and Validation Software either at District/Mandal level.

Printing of School Report Cards after data entry and re-verification by HMs.
:
27-10-15 to 21-11-15
18
Removal of Errors/Discrepancies in the data
:
23-11-15 to 30-11-15
19
Merging of Mandal wise data at District level after removal of errors
:
01-12-15 to 03-12-15
20
Submission of district data to State Head Office
:
04-12-15 to 09-12-15
21
Error Checking at State Level
:
10-12-15 to 12-12-15
22
Merging of District level data at State Project Office
:
13-12-15 to 17-12-15
23
Printing and distribution of school report cards to all schools in the state
:
18-12-15 to 27-12-15
24
Submission of data to NUEPA , EdCIL(TSG) & MHRD
:
31-12-15
25
Dissemination of data at state, district and Mandal levels
:
01-01-16 to 10-01-16
26
Printing of a booklet on educational statistics
:
11-01-16 to 25-01-16
27
Generation of tables for Planning
:
3rd week of Jan’16